Week 7
Report date - 20 February 2009
Progress
Brick and blockwork has been built upto scaffold height and the first lift scaffold has been erected.
Delays actual / anticipated
No further delays have been reported.
Health, Safety & Environmental
Site accommodation is provided comprising of a site office / combined meeting room stacked on top of a combined canteen / toilet block with mains services connected. All statutory Notices are displayed.
Works continue to progress in line with the Construction Phase Health & Safety Plan which will be updated as and when required.
Deliveries to site will be controlled with delivery instructions issued to all suppliers containing the site postcode, were possible all deliveries will be on rigid vehicles with a moffit forklift truck, larger deliveries will use the main road within the University grounds. A haulage road has been provided to the rear off the build area to allow access for material deliveries.
Waste segregation will be carried out mainly off site due to the compact nature of the area in which the Project is being constructed in, however all wastage from blocks are being put into Hippo bags and will be collected at the end of the project and recycled by Tarmac.
NHBC
The NHBC are carrying out Building Control and Warranty Inspections. The Inspector will be visiting Site regularly as per there key stage inspections requirements.
Project team on site
Andy Berwick - Lovell - Build Manager
Bricklayers - 2
Scaffolders - 3
Products and Services installed this week
Scaffolding supplied by Derwent Scaffold
back to top