Week 10


Scaffolding around house site - 9 March13 March 2009 

 

Progress


Week 10 has been good during the week with brickwork complete to the middle band and scaffold erected.

Safety Manager Visits and Audits


A site audit was carried out on Friday 27th February, no issues were raised and paperwork was found to be in order. All weekly inspections are upto date.


Project team on site


Andy Berwick - Lovell - Build Manager 9 March floor errected
Forklift Driver - 1 (shared with another nearby Lovell scheme)
Scaffolders - 4
Bricklayers - 2


Products and Services installed this week

Tarmac Topfloor floor planks - Hollowcore - Code level 6 home 


Photos


See all the photos from the Build

  


back to top

Tarmac poll

How many different types of concrete do Tarmac offer?


Question mark

Did you know?

Fact 16

We need to reduce CO2 emissions by up to 80% by 2050 in order to avoid dangerous climate change.
Source: Energy Saving Trust 2008