Week 36


18 September 2009

Progress 
 

The pellet store has been completed.  The soakaway from the rainwater harvesting tank has been installed.  The base for the cycle store has been concreted.  All slabbing has been completed and gravel margins stoned up.

The front and rear gardens have been top soiled and the porous drive installed.  Both properties have been cleaned and all surplus materials removed from site.

Landscaping is booked for Monday 28 September. The boiler is to be commissioned following the electric connections being completed. Vinyl flooring is to be fitted along with final paint touch up and clean.


Read more on:


 

 

Project team on site

Andy Berwick - Lovell - Build Manager
Joiners – 2
Groundworkers - 2
Plumber - 1 



Photos


See all the photos from the Build



back to top

Tarmac poll

How many different types of concrete do Tarmac offer?


Question mark

Did you know?

Fact 29

By 2050, 56% of people want cars to be very low carbon and powered by fuel cells or electricity.
Source: Energy Saving Trust 2008