Week 30
31 July 2009
Progress
Painting has been completed in the code 4 home. Plumbing has also been filled and domestic water supply tested in both homes. The flue has been installed to the bio mass boiler.
Painting work has started in Code 6 home by emulsion being applied to walls and ceiling. The undercoating woodwork will be starting soon.
The electrician has completed the second fix to the code 6 home.
Week 29 – 20 July
Renderer started on code 6 home by fixing Insulation. Painting and deocrating has been completed decoration in the code 6 home. Bio mass boiler flue and fitted shower screens to both homes.
Week 30 – 27 July
The joiners fitted internal doors and ironmongery. The rainwater harvesting tank has been delivered ready for Tarmac Dry porous asphalt system to be installed.
Project team on site
Andy Berwick - Lovell - Build Manager
Joiners – 2
Apprentice joiner - 1
Plumber - 1
Electrician - 2
Painter - 2
Renderer - 2
Considerate Constructors
The development is registered with the Considerate Constructor Scheme and signage is displayed. The first visit took place on 18 May. 34 points were awarded with a 5 in the Responsible category, with the monitor writing very positive comments regarding the scheme. See more in Tarmac Home receives scores for high level beyond compliance.
The second monitor visit was carried out on 27 July. See more in Considerate Constructor Scheme says Tarmac Home is "An exceptionally good site".
Photos
See all the photos from the Build
back to top