Week 1
Report date - 12 January 2009
Works commenced on site on Monday 5th January.
The foundations were excavated on Tuesday 6th and they were concreted on the 7th January.
Foundation blockwork commenced Friday 9th January.
Considerate Constructor Scheme
The development will be registered with the Considerate Constructor Scheme. A banner will be displayed on the fencing.
NHBC
The NHBC are carrying out Building Control and Warranty Inspections. The inspector will be visiting the site regularly as per their key stage inspectation requirements.
Project team on site
Staff and labour on site consist of:
Building Manager 1
Groundworkers 2
Machine Driver 1
Groundworker Engineer 1
Groundworker Bricklayers 4
Plumber 1
Electricians 2
Build Completed
1. Levelling the ground
2. Dig out trenches and concrete
3. Foundation block work
Below DPC (Damp proof coursing) Brick and blockwork
4. Install drainage for ground floor
5. Install ground floor
Products and Services installed this week
Tarmac Low Carbon Concrete
Tarmac Foundation Blocks
Photos from Week 1 of Build