Week 1

 
Report date - 12 January 2009 
Works commenced on site on Monday 5th January.
The foundations were excavated on Tuesday 6th and they were concreted on the 7th January.
Foundation blockwork commenced Friday 9th January.

Considerate Constructor Scheme

 
The development will be registered with the Considerate Constructor Scheme. A banner will be displayed on the fencing.

NHBC


The NHBC are carrying out Building Control and Warranty Inspections. The inspector will be visiting the site regularly as per their key stage inspectation requirements.

Project team on site


Staff and labour on site consist of:
Building Manager 1
Groundworkers 2
Machine Driver 1
Groundworker Engineer 1
Groundworker Bricklayers 4
Plumber 1
Electricians 2


Build Completed


1. Levelling the ground


2. Dig out trenches and concrete

3. Foundation block work
Below DPC (Damp proof coursing) Brick and blockwork

4. Install drainage for ground floor

5. Install ground floor

 

Products and Services installed this week

 
Tarmac Low Carbon Concrete
Tarmac Foundation Blocks

 

Photos from Week 1 of Build


See all the related photos from on site build.







back to top

Question mark

Did you know?

Fact 5

More and more home premises in the UK are being built to exacting environmental standards, such as BREEAM, and so specifiers need to be confident about the products they select.  Many UK masonry manufacturers have had their product ranges checked by independent assessors to certify environmental performance – many achieve the highest rating of A or A+.

See the more information on the Code for Sustainable Homes