Week 16
17 April 2009
Progress
The roof has progressed as far as possible until the PV panels are fitted on 21 April.
Internally, the Code 4 property has been first fixed by the joiners and the plasterer is progressing the parge coat on the external walls.
In the Code 6 property, stairs have been fitted and first floor screed with Tarmac Truflow screed, the plasterer has boarded the first floor ceiling – ready for early air tests to be carried out once the windows and doors are fitted.
Also during week 16, the windows and doors to Code 4 property will be installed, complete with electrical and plumbing first fixes to the Code 4 Plot. The solar PV panels to roof and roof tiling will be completed. The first fix joinery to the Code 6 property is progressing.
Project team on site
Andy Berwick - Lovell - Build Manager
Forklift Driver - 1 (shared with another nearby Lovell scheme)
Screeders - 2
Joiners – 2
Painter - 2
Roof tilers - 2
Plasterer - 2
Products and Services installed this week
Tarmac Truflow screed
Photos
See all the photos from the Build
back to top