Week 16


17 April 2009

Progress


The roof has progressed as far as possible until the PV panels are fitted on 21 April.

Internally, the Code 4 property has been first fixed by the joiners and the plasterer is progressing the parge coat on the external walls.

In the Code 6 property, stairs have been fitted and first floor screed with Tarmac Truflow screed, the plasterer has boarded the first floor ceiling – ready for early air tests to be carried out once the windows and doors are fitted. 

Also during week 16, the windows and doors to Code 4 property will be installed, complete with electrical and plumbing first fixes to the Code 4 Plot.   The solar PV panels to roof and roof tiling will be completed.  The first fix joinery to the Code 6 property is progressing.
 

Project team on site

Andy Berwick - Lovell - Build Manager
Forklift Driver - 1 (shared with another nearby Lovell scheme)
Screeders - 2
Joiners – 2
Painter - 2
Roof tilers - 2
Plasterer - 2

Products and Services installed this week

Tarmac Truflow screed

Photos


See all the photos from the Build



back to top

Tarmac poll

How many different types of concrete do Tarmac offer?


Question mark

Did you know?

Fact 29

By 2050, 56% of people want cars to be very low carbon and powered by fuel cells or electricity.
Source: Energy Saving Trust 2008