Week 12

27 March 2009
Progress
Roof trusses have been lifted onto the Plots ready to be spread and fixed in place.
Project team on site 
Andy Berwick - Lovell - Build Manager
Forklift Driver - 1 (shared with another nearby Lovell scheme)
Scaffolders - 2
Joiners – 2
Apprentice Joiner - 1
Products and Services installed this week
Roof trusses
Photos
See all the photos from the Build