Week 11


20 March 2009

Progress


Brickwork is now complete to wallplate and the fourth lift scaffold erected plus internal birdcage scaffolds ready for the roof to be installed.


 

Project team on site

Andy Berwick - Lovell - Build Manager
Forklift Driver - 1 (shared with another nearby Lovell scheme)
Scaffolders - 4
Bricklayers - 2

Products and Services installed this week

Tarmac Topfloor floor planks - Hollowcore - Code level 6 home 

Photos


See all the photos from the Build

back to top

Tarmac poll

How many different types of concrete do Tarmac offer?


<div class=did_you_know>
<div>
<img height=86 alt="Question mark" src="/images/page/did_you_know_img.jpg" width=71>
</div>
<h3>
Did you know?</h3>
<p>
Fact 37</p>
<p>
A timber frame house will need air conditioning approximately 20 years before a concrete building.<br>
Source:&nbsp;<a href="http://www.tarmachomesproject.co.uk/why_masonry/benefits_of_thermal_mass/whole_life_performance_research.aspx">
Whole Life Performance Research by the Concrete Centre </a>
</p>
</div>