Week 11
20 March 2009
Progress
Brickwork is now complete to wallplate and the fourth lift scaffold erected plus internal birdcage scaffolds ready for the roof to be installed.
Project team on site
Andy Berwick - Lovell - Build Manager
Forklift Driver - 1 (shared with another nearby Lovell scheme)
Scaffolders - 4
Bricklayers - 2
Products and Services installed this week
Tarmac Topfloor floor planks - Hollowcore - Code level 6 home